08 April 2019

Voting now closed

Voting for the concept designs has now closed. Thank you to everyone that voted.
The City has collated all feedback and is currently working on updating the concept design. Once updated the revised concept will be posted online for viewing.
16 March 2019

Community Engagement Session # 1

The first community engagement session was held on Saturday 16th March from 10am - 12pm. We received lots of great feedback from the community that will help shape the project.
16 March → 18 March 2019

Community Engagement Sessions

Community engagement sessions are planned for Saturday 16th March 10am -12pm and Monday 18th March 3 - 5pm in the courtyard between the Leisureplex and Library.
City of Canning staff and the landscape architect will be on hand to discuss the concept plans and listen to feedback.
December 2017

Riverton Leisureplex Master Plan Development

A concept master plan was prepared following internal stakeholder engagement.
Previous survey feedback was used to guide master plan concepts along with information from brainstorming sessions.
28 August 2018

Budget Adoption for Design Consultant

Funds were approved as part of the budget process to engage a design consultant for the courtyard activation project.
03 December 2018

Award of contract for design

The City has engaged Woodward Design as of the 3rd December 2018. They will be responsible for developing three concept plans for this space.